Resources in Graphical Planner

By default, no resources are provided in Graphical Planner.

When you Get All Data from Manufacturing into Graphical Planner, using Graphical Planner's Data Transfer Menu, your Manufacturing resources are imported into Graphical Planner.

Graphical Planner is a single constraint scheduler, and works by scheduling the primary resource that you specify in Manufacturing. In the Manufacturing Planning Settings Graphical Planner tab, you specify whether the primary resource is labour or machine. This depends on whether your output is constrained primarily by your machine resources, or by your staffing levels.

You can edit resources in Graphical Planner after importing them from Manufacturing.